For scenario's when a portion of a block has been sprayed
In some scenarios, you may not complete a whole block and wish to record the portion which has been sprayed.
1. Create your spray diary as per normal
Enter in all spray details, including Operator, Machine, Chemicals, Select the relevant blocks etc.
2. Double click on the block that has not been completed, and a popup will appear.
3. Select 'Change Percentage of Block Sprayed'
4. Another window will appear, enter the % that has been sprayed, then select OK.
You will then see the % has changed on the block list, and the total hectares and associated calculations (with chemicals etc.) will adjust accordingly.
An automated comment will also appear in the comments box. This comment pulls through to some reports, such as the Spray Diary Report.